In order to ensure safety, any person
wishing to dig in New Jersey is required by law to call for a utility
mark-out three days before any excavation.
The New Brunswick Campus is a member of the Garden State Underground Plant
Location Service. This service enables people, who wish to dig on any of
the New Brunswick Campuses, an easy method of determining the location of
pipe, line, or conduit which are, housed and hidden underground. Call
1-800-272-1000 (24 hours a day, 365 days a year) to request a Utility
Mark-Out.
When requesting a Utility Mark-Out, you are asking that any underground
pipes, lines or conduit which might be passing through your dig site, be
identified using a color coded spray paint or flag method on the ground
surface.
|
Please follow the steps below to request your
Utility Mark-Out:
1) Before calling for a mark-out, please have the following information:
|
|
•
Caller's Name and Title
• Caller's Phone Number and Fax Number
• Contractor Name and Address
• Who the Work is Being Done For
• Dig Location; County, Municipality
• Street Address of Intended Excavation Site
• Nearest Intersection to Excavation Site
• Type of Work
• Extent of Work, Depth
• Start Date and Time
|
2) Call: 1-800-272-1000 (24 hours a day, 365
days a year)
3) Fax: a sketch, print, or written description of the mark-out area to
1-732-445-0007 to the attention of the Water Services Supervisory
Engineer.
4) A "Utility Mark-out Confirmation" will be faxed to you when all
Rutgers' electric, water, sewer, high temperature hot water, air lines,
and chilled water lines, have been marked.
|
|
Mark-Out Will Conform
to ULCC Uniform Color Codes: |
| |
 |
Electric Power Lines, Cables, and Lighting Cables |
| |
 |
Gas,
Oil, Steam, Petroleum, Hot Water, Chilled Water, Air & Gaseous Materials |
| |
 |
Communication, Alarm, Signal Lines, Cable and Conduit |
| |
 |
Water, Irrigation, and Slurry Lines |
| |
 |
Sewer
and Drain Lines |
| |
 |
Temporary Survey Markings |
| |
 |
Proposed Excavation |
|